MIL-DTL-28788C
in 4.7.11, there shall be no change in operation, no evidence of broken, deformed, displace, or loose
parts, and the operating points shall be within the tolerances specified (see 3.1).
3.15.1 Method I (shock, specified pulse). When switches are tested as specified in 4.7.11.1, closing
of open contacts and chatter of closed contacts shall not exceed 10 microseconds, unless otherwise
3.15.2 Method II (when specified, see 3.1) (high-impact shock). When switches are tested as
specified in 4.7.11.2, closing of open contacts and chatter of closed contacts shall not exceed 20
3.16 Vibration. When switches are tested as specified in 4.7.12, there shall be no opening of
closed contacts, nor closing of open contacts, in excess of 250 broken, deformed, displace, or loose parts
and the operating points shall be within the tolerances specified (see 3.1).
3.17 Thermal shock. When switches are tested as specified in 4.7.13, there shall be no mechanical
or electrical damage.
3.18 Moisture resistance. When switches are tested as specified in 4.7.14, the insulation
resistance immediately after conclusion of the test shall be greater than 2 megohms at 500 Vdc. At the
end of the drying period, the insulation resistance shall be as specified in 3.19. At the conclusion of the
test, there shall be no evidence of corrosion or mechanical damage.
3.19 Insulation resistance. When measured as specified in 4.7.15, the insulation resistance
between all insulated terminals and enclosures shall be not less than 500 megohms.
switches are tested as specified in 4.7.16, there shall be no flashover, arcing, or current flow in excess of
500 microamperes.
3.21
3.21.1 Watertight. When switches are tested as specified in 4.7.17.1, there shall be no leakage as
evidenced by a continuous stream of bubbles.
3.21.2 Hermetic. When switches are tested as specified in 4.7.17.2, the leakage rate shall not
-8
exceed 1x10 standard atmospheric cubic centimeters per second (atm cc/sec).
3.22 Contact resistance. When switches are tested as specified in 4.7.18, the initial resistance
shall not exceed 100 milliohms. The final resistance at completion of endurance testing shall not exceed
250 milliohms.
3.23 Endurance. When tested as specified in 4.7.19, there shall be no evidence of malfunction or
damage during or after the test, and switches shall meet the requirements of 3.8.
subsequent operating characteristics shall be as specified (see 3.1), and they shall be mechanically and
electrically operative at the conclusion of the test.
shall be no explosion within the test chamber, whether or not explosion occurs within the switch.
Switches shall be mechanically and electrically operable at the conclusion of the test.
6